I-880 Widening ( SR 237 to US 101)

Description: On I-880 between Old Bayshore Highway in the City of San Jose and Route 237 in the City of Milpitas - Add HOV lane in both directions

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Clara
City Milpitas, San Jose
Zip Code 95035, 95112, 95131
 
Senate District
10, 13
Assembly District 20, 22, 24
Congressional District 15, 16
 
Caltrans District
04
 
 
County/State Route Santa Clara 880
Postmile Begin/End 4.4 8.7
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  19,986    19,186  
Lane Miles Added (HOV)  8.4    8.4  
Peak Period Time Savings (minutes)  1,458,964    1,458,964  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Santa Clara Valley Transportation Authority Gene Gonzalo (408) 952-4236   gene.gonzalo@vta.org
Design (PS&E) Phase
Santa Clara Valley Transportation Authority Gene Gonzalo (408) 952-4236   gene.gonzalo@vta.org
Right of Way Phase
Santa Clara Valley Transportation Authority Gene Gonzalo (408) 952-4236   gene.gonzalo@vta.org
Construction Phase
Caltrans Francis Mensah (510) 622-5946   francis_mensah@dot.ca.gov
 
Corridor System Management Plan
Caltrans Juliana Gum (510) 286-4579   juliana_gum@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$71,600 $-31,758 $39,842
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$23,400 $-1,440 $21,960
 
Total**** $95,000 $-33,198 $61,802

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$5,500 $0 $5,500 $3,147
Design(PS&E)
$6,200 $0 $6,200 $7,407
Right of Way
$8,100 $0 $8,100 $5,545
Construction
$75,200 $-33,198 $42,002 $38,492
 
Total* $95,000 $-33,198 $61,802 $54,591

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2007 

06/01/2009 
 

 
07/01/2007 

06/01/2009 
100  07/02/2007 

06/26/2009 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2009 

02/01/2011 
 

 
06/01/2009 

02/01/2011 
100  11/02/2007 

02/28/2011 
19 

-1 
Begin Right of Way Phase

End Right of Way Phase
06/01/2009 

02/01/2011 
 

 
06/01/2009 

02/01/2011 
100  06/30/2009 

02/28/2011 
-1 

-1 
Begin Construction Phase

End Construction Phase
06/01/2011 

07/01/2013 
 

 
06/01/2011 

07/01/2013 
100  12/14/2011 

04/04/2014 
-7 

-9 
Begin Closeout Phase

End Closeout Phase
08/01/2013 

08/01/2014 
 

 
08/01/2013 

08/01/2014 
100  04/05/2014 

06/20/2017 
-8 

-35 
Corridor System Management Plan
Adoption Date 06/01/2008    06/01/2008  100  09/01/2010  -27 
Implementation Date 06/01/2008    06/01/2008  10/01/2010  -28 
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 19,986 19,186
Lane Miles Added (HOV) 8.4 8.4
Peak Period Time Savings (minutes) 1,458,964 1,458,964

Bond Funding Cost
Adopted:
$71,600,000
Current Approved:
$39,842,000
Actual Expenditures:
$36,741,000

 

Status as of December 31, 2023.